Luton: damp and repairs
What Luton Borough Council publishes about its own performance, the deadlines that bind it, and the free routes when repairs stall.
This page applies to England. The law is different in Wales, where Awaab's Law does not apply at all. See our Wales guidance.
What stands out in Luton's figures
Luton reported 0.8% of homes failing the Decent Homes Standard, below the council median of 3.3%. Worth knowing that landlords assess their own stock and the regulator publishes what it receives without auditing it, so a low figure can mean good homes or can mean not every home has been surveyed.
100% of emergency repairs were completed in target against 83.3% of non-emergency ones, a gap of 17 points. That pattern usually means resource is being pulled towards whatever is on fire, which is cold comfort if your problem is the slow kind that only becomes an emergency later.
Luton received 32 stage one complaints per 1,000 homes against a median of 53.9, while overall satisfaction was 70.4% against a median of 71.8%. A low complaint rate alongside low satisfaction is not obviously contentment. It is at least as consistent with tenants not complaining, or not knowing how. That reading is ours rather than something the data states.
The regulator cautions against comparing landlords on individual measures without allowing for how the survey was run. Luton's was predominantly internet, and method affects who answers: online surveys tend to reach people who are comfortable online and already engaged with the landlord. Region, tenant age and the share of supported housing all move these numbers too.
Against the all-landlord median of 0.5% in the table below, Luton's 0.8% looks poor. Against other councils, where the median is 3.3%, it looks good. Councils and associations are not alike on stock condition and the council figure is the fairer comparison here.
What binds them regardless
Everything above is Luton measuring itself against its own promises. Awaab's Law is different, because it is law and it overrides them. Emergency hazards: 24 hours to investigate and make safe. Damp or mould posing a significant risk of harm: 10 working days to investigate, a written summary within 3 working days of finishing, safety work started within 5. When the clock actually starts.
Luton's 2024-25 return in full
| Measure | Luton | Sector median |
|---|---|---|
| Stage 2 complaints answered in time | 97.9% 9 points better than the median | 88.9% |
| Stage 1 complaints answered in time | 82.2% 7.7 points worse than the median | 89.9% |
| Satisfaction with the approach to complaints | 27.9% 7.6 points worse than the median | 35.5% |
| Emergency repairs inside their own target | 100% 5.1 points better than the median | 94.9% |
| Satisfaction with the repairs service | 78.5% 4.9 points better than the median | 73.6% |
| Satisfaction that the home is safe | 73.9% 3.7 points worse than the median | 77.6% |
| Satisfaction with time taken on the last repair | 72.7% 3.2 points better than the median | 69.5% |
| Satisfaction that the home is well maintained | 73.6% 1.7 points better than the median | 71.9% |
| Non-emergency repairs inside their own target | 83.3% 0.8 points better than the median | 82.5% |
| Homes not meeting the Decent Homes Standard | 0.8% about the same as the median | 0.5% |
If a repair is not happening
Put it in writing and keep the reference, because that date is what every later deadline counts from. If nothing moves, make a formal complaint rather than another chaser. They must acknowledge within 5 working days and respond within 10 of that, then stage two must be handled by someone not involved first time and answered within 20 working days.
How council complaints work, and after that the Housing Ombudsman Service, which is free, can order the repair as well as compensation, and takes no percentage. What to ask before signing with anyone.
If it is damp or mould Start here, whoever your landlord isCommon questions
What is Luton's target for a repair?
30 days for a non-emergency responsive repair, and 24 hours for an emergency. They met the non-emergency target 83.3% of the time in 2024-25. The median target across the 178 landlords we hold data for is 28 days.
This is their own service target, not a legal deadline. The law requires repairs in a reasonable time, which is not defined and depends on the problem.
How many Luton homes fail the Decent Homes Standard?
62 of 7,592, which is 0.8%. The median council reported 3.3%.
These are self-reported figures and the regulator publishes them without auditing them, so they are a reasonable basis for a question and a poor basis for a conclusion. Every landlord ranked on this measure.
What if Luton misses a deadline?
Complain formally, using the words "I am making a formal complaint", then escalate to stage two, then take it to the Housing Ombudsman Service. All three are free and you keep every penny of any award. Luton answered 82.2% of stage one complaints in time in 2024-25, so diarise your dates.
Do these figures measure damp and mould?
No. There is no damp and mould measure anywhere in the Tenant Satisfaction Measures, for this landlord or any other. Damp can make a home fail the Decent Homes Standard through the hazard route, but nothing here counts damp cases.
Figures contain public sector information licensed under the Open Government Licence v3.0. Source: Regulator of Social Housing, Tenant Satisfaction Measures 2024-25 (v1.1), published 4 November 2025. Reported by the landlord for the year to 31 March 2025 and not independently audited.